SDSC Data Center UPS Maintenance, 6/20-6/21/2011, Non-disruptive

Title: SDSC Data Center UPS Maintenance, Non-disruptive
Description: CPT has planned maintenance for two of SDSC’s UPS systems. the scope includes
replacing a broken display and replacing one bank of batteries that are EOL. UPS Systems will be put in bypass and there should be no service outage experienced by customers.
Start Date: 2011-06-20
Start Time: 7:00
End Date: 2011-06-21
End Time: 17:00